Misplaced Pages

Highbank Power Station

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.
Hydro power station in New Zealand

Highbank Power Station
Image of the generating house and transmission equipment.
CountryNew Zealand
LocationAshburton District
Coordinates43°34′23″S 171°44′08″E / 43.5731°S 171.7355°E / -43.5731; 171.7355
StatusOperational
Construction began1939 (1939)
Commission date16 June 1945
(79 years ago) (1945-06-16)
OwnerManawa Energy
Operator
Site area49.5 hectares (122 acres)
Hydraulic head104 m (342 ft)
Maximum discharge rate40 m/s (1,400 cu ft/s)
Power generation
Nameplate capacity26.5 MW
Annual net output98 GWh
External links
WebsiteHighbank Power Scheme
CommonsRelated media on Commons
[edit on Wikidata]

The Highbank Power Station is a small run-of-the-river-hydroelectric power station in the Ashburton District of the South Island of New Zealand. Owned and operated by Manawa Energy, the station generates power from the Rangitata Diversion Race (RDR) irrigation scheme when agricultural water demand is low. Water is discharged into the Rakaia River when the station is generating. On 16 June 1945 (1945-06-16) the Minister of Works, Bob Semple, opened the power station, and "set the 36,000bhp in motion". Additional equipment installed at the site in 2010 enables pumping of water from the Rakaia River back up the penstock to increase the water availability in the RDR for agricultural irrigation during the peak summer months.

Construction

The Highbank Power Station was constructed as part of the Rangitata Diversion Race (RDR) irrigation scheme by the Public Works Department.

The primary purpose of the RDR scheme was for the irrigation of farmland, not the generation of electricity. This irrigation diversion race is the source of the water for the Highbank Power Station. When agricultural demand for water is low the water is used by the station to generate electricity, this is typically during the winter months.

Work began in the early 1940s, starting with the construction of an access road.

The outbreak of World War II saw the project delayed due to manufacturing, material, and manpower shortages. The project's completion in June 1945 followed the completion of the RDR in September 1944.

An unfortunate event was the sinking by enemy action of the ship which was carrying to New Zealand the stator for the generator at Highbank. This necessitated the manufacture of a new stator in England.

There was considerable damage by flooding in the area of the Highbank irrigation and power scheme due to floods in February 1945. This necessitated the village of Highbank being relocated 390 m (0.24 mi) upstream of the powerhouse and a new approach road made.

Power house

The SE face of the power house, and the discharge race.

Construction began in 1939, with the power house structure finished in 1942. The modern reinforced concrete structure is some 37 metres (120 ft) long and 16 metres (52 ft) wide. The height of approximately 16 metres (52 ft) allowed for the installation of both the 90-ton crane, and 10-ton auxiliary hoist.

Generation equipment

Generator and turbine

Both the generator and turbine were manufactured by English Electric and installed from 1942 until the commissioning in 1945. The generator installed was the largest single generating unit in New Zealand at the time of its installation.

The single vertical shaft generator is driven by a 36,000 bhp (27 MW) Francis turbine. The English Electric generator is a 20‑pole unit rated for 26.5 MW output with a synchronous speed of 300 rpm.

Transmission

Power is generated at 11 kV and stepped up at the station to 66 kV for transmission via a 66 kV spur line to Methven connecting to the rest of the EA Networks 66 kV system at Methven Substation.

Upgrades

Early years

Original turbine runner replaced during repair, now on display

In the 1970s the station generation capacity had reduced to approximately 65% of the original rated capacity due to sediment build-up and wear on mechanical components. This led to the turbine runner being replaced along with improvements in sediment control at the canal intake and ongoing removal of sediments to reinstate the original performance

Pump station

Further information: Barrhill-Chertsey irrigation scheme
Pumps used to send water from the Rakaia River back up the penstock to the RDR

In 2010, TrustPower (now Manawa Energy) installed a river intake, fish screening, and pumping facilities to deliver the water from the Rakaia River to the RDR using some of the existing Highbank Power Station facilities. The Highbank Power Station site has been equipped with an array of six 1.5 MW pumps that allow it to take water from the Rakaia River and pump it up the power station penstock 104 metres (342 ft) into the RDR. The water is then available for irrigators to use.

TrustPower (now Manawa Energy) generation manager Mike Kedian believed pumping water back through the penstock was a New Zealand first.

Pumping water up hill is not without its challenges, and one of these is the volume and pressure of the water contained in the pipeline when being pumped. In order to protect the penstock from pressure fluctuations an air-chamber has been installed adjacent to the pump station to maintain pipeline pressure within acceptable bounds.

Generator and turbine replacement 2025

Manawa Energy plans to replace the existing assets with one new 29 MW turbine and a new generator. Replacement of both generator and turbine should provide for a more-efficient generation of electricity using the available water, and is expected to increase output by 8 GWh per year. The project is estimated by Manawa Energy to take 18 months and cost NZ$30.5M. Replacement commenced in October 2024. The nearly 80-year-old equipment had reached end of life, and so, along with the generator and turbine, other mechanical and electrical equipment on the site will be replaced.

Avoiding out-of-phase synchronisation

Generators and their step-up transformers are designed to withstand the internal forces that occur when an electrical short circuit fault occurs close to the power station. However, generators and step-up transformers are still vulnerable to severe damage if a network event causes an out-of-phase synchronisation. Highbank Power Station is potentially exposed to a risk of out-of-phase synchronisation resulting from manual or automatic switching on the 66 kV network. To manage this risk, the historic practice of EA Networks has been to avoid the use of automatic reclose on the 66 kV network, and to ensure that the Highbank generator is disconnected before manually closing circuit breakers. These precautions add complexity to network operations and can delay restoration of circuits after a fault. EA Networks plans to install phasor measurement units (or synchrophasors) on their 66 kV network in 2025 to enable automatic re-closing of 66 kV circuit breakers if the conditions for closure are suitable and will not produce an unacceptable out-of-phase synchronisation.

See also

References

  1. ^ Highbank Power Station. Wellington, N.Z. : Govt Print., 1958. 1958. Retrieved 2 January 2025.
  2. "Rating Information Details". ADC. Ashburton District Council. Retrieved 2 January 2025.
  3. "CRC011249 Consent for water discharge". ECAN. Environment Canterbury. Retrieved 2 January 2025.
  4. ^ "Highbank Power Scheme". Manawa Energy. Retrieved 2 January 2025.
  5. ^ "Water and Power - Highbank Station - Started by Mr Semple". Evening Post. Vol. CXXXIX, no. 142. 18 June 1945. p. 4 – via Papers Past.
  6. ^ New Zealand National Film Unit (19 September 2012). "Weekly Review No. 202 (1945)" (Video). Archives New Zealand. Retrieved 2 January 2025.
  7. ^ "EA NETWORKS ASSET MANAGEMENT PLAN 2023–33" (PDF). EA Network. EA Networks. Retrieved 2 January 2025.
  8. "The Hydro Station.", The Ashburton Guardian, p. 4, 17 January 1940, retrieved 12 January 2025
  9. "Floods during construction". New Zealand Historic Weather Events Catalogue. National Institute of Water and Atmospheric Research. Retrieved 3 January 2025.
  10. Greenhill, Marc (15 July 2010). "Pumps set to revive irrigation scheme". Stuff. Archived from the original on 16 May 2020.
  11. "Power company invests in irrigation scheme" (PDF). worldpumps.com. Retrieved 3 January 2025.
  12. ^ "FY25 Interim Results Presentation" (PDF). Manawa Energy.
  13. "Annual Shareholder Meeting 2023" (PDF). Manawa Energy. Retrieved 3 January 2025.
  14. "IEEE Power System Relaying and Control (PSRC) Committee Working Group J20: Practices for Generator Synchronizing Systems" (PDF). IEEE Power & Energy Society - Power System Relaying and Control Committee. April 2024. p. 4. Retrieved 15 January 2024.
Ashburton District, New Zealand
Seat: Ashburton
Populated places
Ashburton
Eastern Ward
Hinds Sub-Division
Rakaia Sub-Division
Western Ward
Geographic features
Facilities and attractions
Government
Organisations
Hydropower
Hydroelectricity generation
Hydroelectricity equipment
Categories: